A pile cap bottom will bear on undisturbed soil with reinforcing steel placed before the concrete is cast. For concrete cast against and permanently exposed to earth, which minimum cover does ACI 318 require?
Correct Answer
A) 3 in.
ACI 318-19 Table 20.6.1.3.1 gives 3 in. as the minimum cover for reinforcement in concrete cast against and permanently exposed to earth. Other choices: 2 in. and 1-1/2 in. belong to formed concrete exposed to earth or weather for different bar sizes, while 3/4 in. is an interior slab, wall, or joist value.
Why This Is the Correct Answer
ACI 318-19 Table 20.6.1.3.1 gives 3 in. as the minimum cover for reinforcement in concrete cast against and permanently exposed to earth.
Why the Other Options Are Wrong
Option B: 2 in.
In concrete work, 2 in. is the wrong selection for Concrete cover: 2 in. is a concrete-cover value for a different exposure/member case; ACI 318-19 Table 20.6.1.3.1 keys this item to 3 in.
Option C: 1-1/2 in.
The trap in C is 1-1/2 in. That selection is wrong because 1-1/2 in. is a concrete-cover value for a different exposure/member case; ACI 318-19 Table 20.6.1.3.1 keys this item to 3 in.; Minimum cover for concrete cast against earth is 3 in.
Option D: 3/4 in.
Choice D gives 3/4 in. Its specific error: 3/4 in. is a concrete-cover value for a different exposure/member case; ACI 318-19 Table 20.6.1.3.1 keys this item to 3 in. The accepted answer is 3 in.
Memory Technique
Link concrete cover to its book condition; a different condition means a different answer than 3 in.
Reference Hint
Open ACI 318-19, Building Code Requirements for Structural Concrete; use ACI 318-19 Table 20.6.1.3.1 to confirm that ACI 318-19 Table 20.6.1.3.1 gives 3 in.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?