Three subcontract bids for the same scope arrive with different inclusions and exclusions. What is the purpose of bid leveling before award?
Correct Answer
A) Compare bids on an equal scope by identifying inclusions, exclusions, gaps, and overlaps
Bid leveling compares bidders on a consistent scope by identifying included work, exclusions, gaps, and overlaps. Other choices ignore scope comparison or change the contracting basis.
Why This Is the Correct Answer
Bid leveling compares bidders on a consistent scope by identifying included work, exclusions, gaps, and overlaps. Other choices ignore scope comparison or change the contracting basis.
Why the Other Options Are Wrong
Option B: Automatically award to the first bid received
Choice B (Automatically award to the first bid received) is rejected because it shifts the question into contract administration money flow.
Option C: The contractor should remove all specification requirements
In procurement and contracting, Remove all specification requirements is the wrong selection for Bid leveling: it leaves out the controlling Bid leveling result: Compare bids on an equal scope by identifying inclusions, exclusions, gaps, and overlaps.
Option D: Convert a lump-sum bid into a time-and-material contract
The trap in D is Convert a lump-sum bid into a time-and-material contract. That selection is wrong because the option answers a paperwork, payment, or bonding issue.
Memory Technique
Link bid leveling to its book condition; a different condition means a different answer than Compare bids on an equal scope by identifying inclusions, exclusions, gaps, and overlaps.
Reference Hint
Open Construction Project Management, 5th Ed. (2022); use the index entry or section for "Bid leveling and scope review" to confirm that Bid leveling compares bidders on a consistent scope by identifying included work, exclusions, gaps, and overlaps.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
