A specification calls for Type M mortar by property specification. Which minimum 28-day compressive strength is associated with that mortar type?
Correct Answer
D) 2,500 psi
ASTM C270 property values list Type M mortar at 2,500 psi minimum average compressive strength at 28 days. Other choices: 750 psi is Type N, 1,800 psi is Type S, and 1,200 psi is not the standard Type M value.
Why This Is the Correct Answer
ASTM C270 property values list Type M mortar at 2,500 psi minimum average compressive strength at 28 days.
Why the Other Options Are Wrong
Option A: 750 psi
The trap in A is 750 psi. That selection is wrong because 750 psi is a different published number than the cited Mortar type strength value; ASTM C270 mortar property specification values supports 2,500 psi; Type M mortar minimum average compressive strength is 2,500 psi.
Option B: 1,200 psi
Choice B gives 1,200 psi. Its specific error: 1,200 psi is a different published number than the cited Mortar type strength value; ASTM C270 mortar property specification values supports 2,500 psi. The accepted answer is 2,500 psi.
Option C: 1,800 psi
Choice C (1,800 psi) is rejected because 1,800 psi is a different published number than the cited Mortar type strength value; ASTM C270 mortar property specification values supports 2,500 psi. The cited answer is 2,500 psi.
Memory Technique
Link mortar type strength to its book condition; a different condition means a different answer than 2,500 psi.
Reference Hint
Open Modern Masonry - Brick, Block, Stone, 9th Ed., 2020; use the index entry or section for "ASTM C270 mortar property specification values" to confirm that ASTM C270 property values list Type M mortar at 2,500 psi minimum average compressive strength at 28 days.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?