A gypsum board level has 1,420 lf of board joints measured from the layout. The foreman adds 10 percent for corners, repairs, and waste. What tape length should be carried?
Correct Answer
D) 1,562 lf
Adjusted tape length is 1,420 x 1.10 = 1,562 lf. Other choices omit waste, round down too far, or apply a 20 percent allowance not stated.
Why This Is the Correct Answer
Adjusted tape length is 1,420 x 1.10 = 1,562 lf. Other choices omit waste, round down too far, or apply a 20 percent allowance not stated.
Why the Other Options Are Wrong
Option A: 1,420 lf
joint tape length, choice a: 1,420 lf equals 1,420. That copies a listed value without completing the operation.
Option B: 1,500 lf
joint tape length, choice b: 1,500 lf backs into 15,000 when divided by 10 percent; the accepted setup gives 15,620 on that same base.
Option C: 1,704 lf
joint tape length, choice d: 1,704 lf backs into 17,040 when divided by 10 percent; the accepted setup gives 15,620 on that same base.
Memory Technique
Store joint tape length with its last math move; nearby answers are usually unfinished versions of 1,562 lf.
Reference Hint
Open Gypsum Construction Handbook, 7th Ed., 2014; use the index entry or section for "Joint tape quantity allowance" to confirm that Adjusted tape length is 1,420 x 1.10 = 1,562 lf.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass