A storm drain pipe is laid directly on large rock fragments in the trench bottom. The crew wants to backfill immediately because the slope is correct. What is the concern?
Correct Answer
A) Pipe bedding must support the barrel uniformly and protect the pipe from point loads
Underground pipe needs proper bedding to support the barrel and prevent point loads that can crack, deform, or settle the pipe. Other choices ignore support and material protection.
Why This Is the Correct Answer
Underground pipe needs proper bedding to support the barrel and prevent point loads that can crack, deform, or settle the pipe. Other choices ignore support and material protection.
Why the Other Options Are Wrong
Option B: Rock bedding always increases pipe flexibility
In mechanical and plumbing, Rock bedding always increases pipe flexibility is the wrong selection for Underground pipe bedding: it solves the wrong trade problem; the field result tied to Underground pipe bedding is Pipe bedding must support the barrel uniformly and protect the pipe from point loads.
Option C: Select slope alone controls pipe performance for underground pipe bedding
The trap in C is Slope alone controls pipe performance. That selection is wrong because the option shifts to a different trade task; the tested Underground pipe bedding function or field correction is Pipe bedding must support the barrel uniformly and protect the pipe from point loads; Underground pipe requires proper bedding and uniform support.
Option D: Base the underground pipe bedding response on metal pipe needs bedding
Choice D gives Only metal pipe needs bedding. Its specific error: it leaves the work at an informal or incomplete stage, while Underground pipe bedding requires Pipe bedding must support the barrel uniformly and protect the pipe from point loads.
Memory Technique
Use the phrase "problem, control, result" for underground pipe bedding; the result side is Pipe bedding must support the barrel uniformly and protect the pipe from point loads.
Reference Hint
Open Pipe and Excavation Contracting, 2011; use the index entry or section for "Pipe bedding and support" to confirm that Underground pipe needs proper bedding to support the barrel and prevent point loads that can crack, deform, or settle the pipe.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?