Why is final stabilization required on disturbed soil?
Correct Answer
D) It prevents exposed soil from continuing to erode after grading work is complete
Final stabilization covers or vegetates disturbed soil so it no longer remains an active sediment source.
Why This Is the Correct Answer
Final stabilization covers or vegetates disturbed soil so it no longer remains an active sediment source.
Why the Other Options Are Wrong
Option A: Document the condition in the daily report and wait for the next final stabilization purpose review
Choice A gives It calculates retainage. Its specific error: it shifts the question into contract administration money flow.
Option B: Treat the item as a closeout correction tied to final stabilization purpose
Choice B (It approves drywall) is rejected because it points to It approves drywall, but.
Option C: Classify final stabilization purpose as a scheduling note only
In site construction, It sizes switchgear is the wrong selection for Final stabilization purpose: it answers the Final stabilization purpose prompt with the wrong practical move.
Memory Technique
Keep final stabilization purpose as a cause-to-effect card with It prevents exposed soil from continuing to erode after grading work is complete on the back.
Reference Hint
Open Developing Your Stormwater Pollution Prevention Plan, EPA 833-R-06-004, 2007; use the index entry or section for "EPA 833-R-06-004 - erosion and sediment controls" to confirm that Final stabilization covers or vegetates disturbed soil so it no longer remains an active sediment source.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
