A hotel elevation has 11 identical punched windows per floor for 6 floors. The owner adds 5 percent attic stock for future replacement. What window count should be ordered?
Correct Answer
A) 70 windows
Base count is 11 x 6 = 66 windows. Adding 5 percent gives 66 x 1.05 = 69.3, rounded up to 70 windows. Other choices omit attic stock, round down, or use a larger allowance.
Why This Is the Correct Answer
Base count is 11 x 6 = 66 windows. Adding 5 percent gives 66 x 1.05 = 69.3, rounded up to 70 windows. Other choices omit attic stock, round down, or use a larger allowance.
Why the Other Options Are Wrong
Option B: 66 windows
window count, choice a: the answer choice lifts 66 windows from the working line Base count is 11 x 6 = 66 windows.
Option C: 69 windows
window count, choice b: 69 windows rounds the 69.3 result down; the accepted path rounds/carries it to 70 in.
Option D: 72 windows
window count, choice d: 72 windows implies about 9.09 percent added to 66; the stated add-on is 5 percent in.
Memory Technique
Remember window count as "base, adjustment, final unit"; the last unit should read 70 windows.
Reference Hint
Open Principles and Practices of Commercial Construction, 11th Ed., 2024; use the index entry or section for "Window unit quantity takeoff" to confirm that Base count is 11 x 6 = 66 windows.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A subcontractor certificate shows lower limits than the subcontract requires. What should the contractor do?
Next Question
A force-account record allows equipment standby at 50 percent of the $740/day operating rate. The machine is on standby for 3 days. What standby amount is supported?