A subcontractor certificate shows lower limits than the subcontract requires. What should the contractor do?
Correct Answer
C) Reject or hold the certificate issue until compliant coverage evidence is provided.
Certificates must be checked against required coverage, endorsements, and limits.
Why This Is the Correct Answer
Certificates must be checked against required coverage, endorsements, and limits.
Why the Other Options Are Wrong
Option A: Use a later change request to handle insurance certificate mismatch after award
The trap in A is Ignore it because any certificate is enough. That selection is wrong because the action skips the timing, documentation, or field-control step needed for Insurance certificate mismatch.
Option B: Apply release final payment immediately to the insurance certificate mismatch condition
Choice B gives Release final payment immediately. Its specific error: it names a financial document or payment mechanism, not the Insurance certificate mismatch action/result stated by Reject or hold the certificate issue until compliant coverage evidence is provided.
Option D: The contractor should use the certificate as a change order
In procurement and contracting, Use the certificate as a change order. is the wrong selection for Insurance certificate mismatch: it shifts the question into contract administration money flow.
Memory Technique
Picture a flashing lip on the jobsite; insurance certificate mismatch is solved by the action that leads to Reject or hold the certificate issue until compliant coverage evidence is provided.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Insurance certificate review" to confirm that Certificates must be checked against required coverage, endorsements, and limits.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A masonry opening head is detailed at 7 ft 4 in. above the slab. Using standard 8 in. CMU coursing, how many full courses reach that height?
Next Question
A hotel elevation has 11 identical punched windows per floor for 6 floors. The owner adds 5 percent attic stock for future replacement. What window count should be ordered?