A force-account record allows equipment standby at 50 percent of the $740/day operating rate. The machine is on standby for 3 days. What standby amount is supported?

Correct Answer

C) $1,110

Standby rate is $740 x 50% = $370/day. For 3 days, standby amount is 3 x $370 = $1,110. Other choices use two days, full operating rate, or one standby day.

Answer Options
A
$370
B
$1,480
C
$1,110
D
$2,220

Why This Is the Correct Answer

Standby rate is $740 x 50% = $370/day. For 3 days, standby amount is 3 x $370 = $1,110. Other choices use two days, full operating rate, or one standby day.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.