A compacted fill requires 1,500 cubic yards in place. Borrow material shrinks 12% from loose to compacted. How many loose cubic yards are needed?
Correct Answer
B) 1,704.5 loose cu yd
If compacted volume is 88% of loose, loose needed is 1,500 / 0.88 = 1,704.5 loose cu yd.
Why This Is the Correct Answer
If compacted volume is 88% of loose, loose needed is 1,500 / 0.88 = 1,704.5 loose cu yd.
Why the Other Options Are Wrong
Option A: 1,320.0 loose cu yd
fill shrinkage quantity, choice b: 1,320.0 loose cu yd is wrong because 1,320.0 loose cu yd implies compacted volume is about 113.64 percent of loose volume; the accepted shrinkage factor is 85 percent in.
Option C: 1,500.0 loose cu yd
fill shrinkage quantity, choice c: 1,500.0 loose cu yd implies compacted volume is about 100 percent of loose volume; the accepted shrinkage factor is 85 percent in.
Option D: 1,680.0 loose cu yd
fill shrinkage quantity, choice d: 1,680.0 loose cu yd implies compacted volume is about 89.29 percent of loose volume; the accepted shrinkage factor is 85 percent in.
Memory Technique
Picture a checkpoint labeled fill shrinkage quantity: finish every operation before accepting 1,704.5 loose cu yd.
Reference Hint
Open Pipe and Excavation Contracting, 2011; use by topic index - earthwork volume / swell / shrink to confirm that If compacted volume is 88% of loose, loose needed is 1,500 / 0.88 = 1,704.5 loose cu yd.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?