A quality-control review flags the following point: what document allocates the contract sum to work categories for pay-application review?
Correct Answer
B) Schedule of values
Schedule of values is the controlling requirement: the distractors are related-looking contract or field terms, but they do not match the cited requirement for review item 271.
Why This Is the Correct Answer
Schedule of values is the controlling requirement
Why the Other Options Are Wrong
Option A: Base the schedule of values response on bid bond
The trap in A is Bid bond. That selection is wrong because it shifts the question into contract administration money flow.
Option C: Base the schedule of values response on notice of award
Choice C (Notice of award) is rejected because it leaves out the controlling Schedule of values result: Schedule of values.
Option D: Base the schedule of values response on warranty call log
In procurement and contracting, Warranty call log is the wrong selection for Schedule of values: the choice would not get the project to Schedule of values, which is the Schedule of values result verified by the source.
Memory Technique
Treat schedule of values like a labeled shelf; only the matching condition belongs with Schedule of values.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Schedule of values" to confirm that Schedule of values is the controlling requirement
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?