A temporary enclosure is proposed on an upper floor before a storm. What should be verified?
Correct Answer
C) Anchorage, wind loading, access, fire egress, and material protection.
Temporary enclosures can affect wind, access, and egress, so they require planning.
Why This Is the Correct Answer
Temporary enclosures can affect wind, access, and egress, so they require planning.
Why the Other Options Are Wrong
Option A: Base the temporary enclosure wind response on final record drawings only
Choice A gives Only final record drawings. Its specific error: the option delays or omits the controlling step.
Option B: Base the temporary enclosure wind response on the project directory
Choice B (Only the project directory.) is rejected because the action skips the timing, documentation, or field-control step needed for Temporary enclosure wind.
Option D: Treat the condition as requiring no check if plastic sheeting is used
The trap in D is No check if plastic sheeting is used. That selection is wrong because the choice would not get the project to Anchorage, wind loading, access, fire egress, and material protection.
Memory Technique
Pair temporary enclosure wind with the real field trigger, then choose the response that produces Anchorage, wind loading, access, fire egress, and material protection.
Reference Hint
Open Construction Jobsite Management, 5th Ed. (2024); use by topic index - material handling / storage / weather protection to confirm that Temporary enclosures can affect wind, access, and egress, so they require planning.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Project Management
60 questions · 70% to pass
