A camera inspection shows a belly in a sanitary run before slab placement. What should happen?
Correct Answer
C) Correct bedding and grade before cover
A belly in a gravity sanitary run should be corrected before the pipe is covered or slab placement makes repair difficult.
Why This Is the Correct Answer
A belly in a gravity sanitary run should be corrected before the pipe is covered or slab placement makes repair difficult.
Why the Other Options Are Wrong
Option A: Accept because water may pass
The trap in A is Accept because water may pass. That selection is wrong because the choice would not get the project to Correct bedding and grade before cover, which is the Sanitary pipe belly correction result verified by the source; Pipe bellies are corrected before cover.
Option B: Make flush after occupancy the answer for sanitary pipe belly correction
Choice B gives Flush after occupancy. Its specific error: the option does not produce the required Sanitary pipe belly correction outcome, Correct bedding and grade before cover.
Option D: The site crew should pour slab first, leaving sanitary pipe belly correction unverified
In site construction, Pour slab first is the wrong selection for Sanitary pipe belly correction: it answers the Sanitary pipe belly correction prompt with the wrong practical move.
Memory Technique
Use the phrase "problem, control, result" for sanitary pipe belly correction; the result side is Correct bedding and grade before cover.
Reference Hint
Open Pipe and Excavation Contracting, 2011; use by topic index - gravity drainage slope / pipe fall to confirm that A belly in a gravity sanitary run should be corrected before the pipe is covered or slab placement makes repair difficult.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?