What total centerline length is shown for the four temporary swale segments?
Correct Answer
C) 94 ft
Both 20 ft end segments are part of the swale and must be included.
Why This Is the Correct Answer
Both 20 ft end segments are part of the swale and must be included.
Why the Other Options Are Wrong
Option A: 62 ft
Choice A adds only 20 ft + 26 ft + 16 ft and misses the final 28 ft segment shown.
Option B: 82 ft
Choice B omits one of the 20 ft swale segments.
Option D: 110 ft
Choice D adds an extra 16 ft that is not labeled on the swale.
Memory Technique
Plan-takeoff cue for temporary swale segment: path labels are quantity labels.
Reference Hint
Open Sheet C-240; locate the named site feature and use the shown dimensions or scale bar exactly as described.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Project Management
60 questions · 70% to pass
