When the reviewer opens the backup package, a foreman is asked verbally to add weekend work, and the contract requires written authorization. What protects payment rights?
Correct Answer
C) Document the direction and follow the change-notice procedure
Document the direction and follow the change-notice procedure is the contract-appropriate response: the distractors either bypass required review, conceal a defect, or create a payment or quality dispute in scenario item 334.
Why This Is the Correct Answer
Document the direction and follow the change-notice procedure is the contract-appropriate response
Why the Other Options Are Wrong
Option A: Select do the work silently for unauthorized change
In procurement and contracting, Do the work silently is the wrong selection for Unauthorized change: the option does not produce the required Unauthorized change outcome.
Option B: The foreman should hide it in retainage
The trap in B is Hide it in retainage. That selection is wrong because the option delays or omits the controlling step.
Option D: Make treat it as warranty the answer for unauthorized change
Choice D (Treat it as warranty) is rejected because it leaves out the controlling Unauthorized change result.
Memory Technique
Pair unauthorized change with the real field trigger, then choose the response that produces Document the direction and follow the change-notice procedure.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Change authorization" to confirm that Document the direction and follow the change-notice procedure is the contract-appropriate response
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass