After prime contract award, contractor buyout is the process of:
Correct Answer
B) Purchasing and subcontracting the work while confirming scope, price, schedule, and terms
Buyout is the post-award process of purchasing materials and awarding subcontracts while confirming scope, price, schedule, and terms. Other choices describe closeout, delay, or document misuse.
Why This Is the Correct Answer
Buyout is the post-award process of purchasing materials and awarding subcontracts while confirming scope, price, schedule, and terms. Other choices describe closeout, delay, or document misuse.
Why the Other Options Are Wrong
Option A: Apply closing the project warranty file to the buyout condition
In procurement and contracting, Closing the project warranty file is the wrong selection for Buyout: it points to Closing the project warranty file, but.
Option C: Stopping all procurement until final completion
Choice C gives Stopping all procurement until final completion. Its specific error: it leaves out the controlling Buyout result: Purchasing and subcontracting the work.
Option D: Replacing the construction documents with daily reports
Choice D (Replacing the construction documents with daily reports) is rejected because the choice would not get the project to Purchasing and subcontracting the work.
Memory Technique
Use buyout as the label and Purchasing and subcontracting the work while confirming scope, price, schedule, and terms as the definition to recall under pressure.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management - Basic, 14th Ed.; use by topic index - procurement and contracting fallback to confirm that Buyout is the post-award process of purchasing materials and awarding subcontracts while confirming scope, price, schedule, and terms.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
