The deck crew inside a controlled decking zone wants to make final deck attachments while the leading edge is still active. What should the superintendent say?
Correct Answer
D) Final deck attachments and shear connectors are not performed in the CDZ
OSHA 1926.760(c)(7) states that final deck attachments and installation of shear connectors shall not be performed in the controlled decking zone. Other choices confuse safety deck attachment with final attachment or ignore the CDZ restriction.
Why This Is the Correct Answer
OSHA 1926.760(c)(7) states that final deck attachments and installation of shear connectors shall not be performed in the controlled decking zone. Other choices confuse safety deck attachment with final attachment or ignore the CDZ restriction.
Why the Other Options Are Wrong
Option A: Proceed because final fastening is safer near the edge
In metals work, Proceed because final fastening is safer near the edge is the wrong selection for CDZ final work: it answers the CDZ final work prompt with the wrong practical move.
Option B: Do final attachments only after the concrete subcontractor arrives
The trap in B is Do final attachments only after the concrete subcontractor arrives. That selection is wrong because the action skips the timing, documentation, or field-control step needed for CDZ final work.
Option C: Proceed if unsecured decking stays under 3,000 sq ft
Choice C gives Proceed if unsecured decking stays under 3,000 sq ft. Its specific error: Proceed if unsecured decking stays under 3,000 sq ft is a different published number than the cited CDZ final work value; 29 CFR 1926.760(c)(7) supports Final deck attachments and shear connectors are not performed in the CDZ.
Memory Technique
Use the phrase "problem, control, result" for CDZ final work; the result side is Final deck attachments and shear connectors are not performed in the CDZ.
Reference Hint
Open 29 CFR Part 1926, Subpart R - Steel Erection; use 29 CFR 1926.760(c)(7) to confirm that OSHA 1926.760(c)(7) states that final deck attachments and installation of shear connectors shall not be performed in the controlled decking zone.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Project Management
60 questions · 70% to pass
