In a CPM schedule, what does free float measure?

Correct Answer

C) Delay possible without moving the next activity's early start

Free float is how long an activity can slip without delaying the early start of any following activity. Total float is how long it can slip without delaying project completion.

Answer Options
A
Delay possible without moving the project finish
B
Time added by the owner through a change order
C
Delay possible without moving the next activity's early start
D
Days between substantial and final completion

Why This Is the Correct Answer

Free float is how long an activity can slip without delaying the early start of any following activity. Total float is how long it can slip without delaying project completion.

Independent practice; verify any reference hint against the edition and category permitted for your booking. Official exam and reference-list sources →

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.