EstatePass
NASCLAGeneral Reqmedium22% of exam part

After the revised drawing is issued, a schedule update shows one late activity has float and another delays completion. Where is recovery focused first?

Correct Answer

C) On the critical-path delay

On the critical-path delay is the contract-appropriate response: the distractors either bypass required review, conceal a defect, or create a payment or quality dispute in scenario item 265.

Answer Options
A
Make on the float activity the answer for critical path
B
Make on completed work the answer for critical path
C
On the critical-path delay
D
Apply on easiest paperwork to the critical path condition

Why This Is the Correct Answer

On the critical-path delay is the contract-appropriate response

Why the Other Options Are Wrong

Option A: Make on the float activity the answer for critical path

Choice A gives On the float activity. Its specific error: it leaves out the controlling Critical path result: On the critical-path delay.

Option B: Make on completed work the answer for critical path

Choice B (On completed work) is rejected because the choice would not get the project to On the critical-path delay, which is the Critical path result verified by the source. The cited answer is On the critical-path delay.

Option D: Apply on easiest paperwork to the critical path condition

The trap in D is On easiest paperwork. That selection is wrong because it points to On easiest paperwork, but.

Memory Technique

Use the phrase "problem, control, result" for critical path; the result side is On the critical-path delay.

Reference Hint

Open Construction Jobsite Management, 5th Ed.; use the index entry or section for "Critical path recovery" to confirm that On the critical-path delay is the contract-appropriate response

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.