A gravity sewer run cannot maintain required slope because of a utility conflict. What should happen?

Correct Answer

C) Stop and get design direction before changing it

Pause the affected installation and obtain coordinated design and utility direction. Changing slope, invert or alignment can affect both drainage performance and the conflicting utility. Backfilling conceals the problem; erosion-control fabric is not a substitute for an approved pipe support detail.

Answer Options
A
Flatten the grade without approval
B
Backfill to conceal the conflict
C
Stop and get design direction before changing it
D
Use silt fence as pipe support

Why This Is the Correct Answer

Pause the affected installation and obtain coordinated design and utility direction. Changing slope, invert or alignment can affect both drainage performance and the conflicting utility. Backfilling conceals the problem; erosion-control fabric is not a substitute for an approved pipe support detail.

Independent practice; verify any reference hint against the edition and category permitted for your booking. Official exam and reference-list sources →

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.