A storm pipe run of 216 ft must fall at 1/8 in. per ft. What total fall is required?
Correct Answer
A) 27.0 in.
Total fall is 216 ft x 1/8 in. per ft = 27.0 in.
Why This Is the Correct Answer
Total fall is 216 ft x 1/8 in. per ft = 27.0 in.
Why the Other Options Are Wrong
Option B: 24 in.
storm pipe fall, choice a: 24 in. implies about 11.11 percent fall over 216 ft; the stated slope is the one used in.
Option C: 29 in. total fall
storm pipe fall, choice b: 29 in. is wrong because 29 in. implies about 13.43 percent fall over 216 ft; the stated slope is the one used in.
Option D: 54 in. total fall
storm pipe fall, choice d: 54 in. implies about 25 percent fall over 216 ft; the stated slope is the one used in.
Memory Technique
Picture a stormwater map labeled storm pipe fall: finish every operation before accepting 27.0 in.
Reference Hint
Open Pipe and Excavation Contracting, 2011; use by topic index - gravity drainage slope / pipe fall to confirm that Total fall is 216 ft x 1/8 in.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
