A project requires bidders to submit safety history, bonding capacity, and comparable project experience before receiving bid documents. What procurement process is this?
Correct Answer
B) Prequalification
Prequalification screens bidders before bidding based on stated qualification criteria. Other choices are closeout or warranty activities, not bidder screening.
Why This Is the Correct Answer
Prequalification screens bidders before bidding based on stated qualification criteria. Other choices are closeout or warranty activities, not bidder screening.
Why the Other Options Are Wrong
Option A: Final payment
The trap in A is Final payment. That selection is wrong because the option answers a paperwork, payment, or bonding issue.
Option C: Close contract execution first and resolve the prequalification record later
Choice C (Punch-list review) is rejected because the option does not produce the required Prequalification outcome, Prequalification.
Option D: Warranty callback
In procurement and contracting, Warranty callback is the wrong selection for Prequalification: it points to Warranty callback, but.
Memory Technique
Link prequalification to its book condition; a different condition means a different answer than Prequalification.
Reference Hint
Open Construction Project Management, 5th Ed. (2022); use the index entry or section for "Prequalification of bidders" to confirm that Prequalification screens bidders before bidding based on stated qualification criteria.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass