A bidder wants approval of a named-equal roofing product before bid day. The procurement documents require pre-bid substitution requests by a stated deadline. What should the bidder do?
Correct Answer
A) Submit the substitution request by the stated pre-bid deadline and rely only on written approval or addendum
Pre-bid substitutions must follow the substitution procedure and deadline, and bidders should rely on written approval or addendum. Other choices bypass the procurement rules or leave required scope out of the bid.
Why This Is the Correct Answer
Pre-bid substitutions must follow the substitution procedure and deadline, and bidders should rely on written approval or addendum. Other choices bypass the procurement rules or leave required scope out of the bid.
Why the Other Options Are Wrong
Option B: Carry the product silently and reveal it after award
Choice B (Carry the product silently and reveal it after award) is rejected because it leaves out the controlling Pre-bid substitution deadline result: Submit the substitution request by the stated pre-bid deadline and rely only on written approval or.
Option C: Assume verbal supplier approval changes the specification
In procurement and contracting, Assume verbal supplier approval changes the specification is the wrong selection for Pre-bid substitution deadline: it leaves the work at an informal or incomplete stage, while Pre-bid substitution deadline requires Submit the substitution request by the stated pre-bid deadline and rely only on written approval or.
Option D: The bidder should omit the roofing scope until the owner decides
The trap in D is Omit the roofing scope until the owner decides. That selection is wrong because it describes work from another assembly, while the Pre-bid substitution deadline item is asking for Submit the substitution request by the stated pre-bid deadline and rely only on written approval or.; Pre-bid substitutions must follow the procurement documents' deadline and written approval procedure.
Memory Technique
Link pre-bid substitution deadline to its book condition; a different condition means a different answer than Submit the substitution request by the stated pre-bid deadline and rely only on written approval or addendum.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Pre-bid substitution procedure" to confirm that Pre-bid substitutions must follow the substitution procedure and deadline, and bidders should rely on written approval or addendum.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass