NASCLAMech/Plumbmedium5% of exam part

On the mechanical plan, find equipment tag WH-13; then read the equipment schedule. What capacity is shown?

Correct Answer

A) 60 gal

Sheet M-810 shows WH-13 on the plan excerpt; the matching schedule row lists 60 gal in the Capacity column.

Answer Options
A
60 gal
B
5 ton
C
800 cfm
D
28 gpm

Why This Is the Correct Answer

Sheet M-810 shows WH-13 on the plan excerpt; the matching schedule row lists 60 gal in the Capacity column.

Why the Other Options Are Wrong

Option B: 5 ton

5 ton is the capacity entry for RTU-11, not for the mark located on the plan.

Option C: 800 cfm

800 cfm is the capacity entry for EF-12, not for the mark located on the plan.

Option D: 28 gpm

28 gpm is the capacity entry for PMP-14, not for the mark located on the plan.

Memory Technique

For mechanical and equipment 11, the graphic tag is the row lock and Capacity is the column lock.

Reference Hint

Open Sheet M-810; locate WH-13 in the plan excerpt before reading the schedule row.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.