A shutdown will affect occupied restrooms in an adjacent area. What is the correct control?

Correct Answer

D) Plan notice, duration, temporary service, approval, and restoration responsibilities.

Utility shutdowns need coordinated notice and temporary measures where occupants are affected.

Answer Options
A
Turn off water without notice
B
Record it only as a warranty item
C
Ask the supplier to approve the shutdown
D
Plan notice, duration, temporary service, approval, and restoration responsibilities.

Why This Is the Correct Answer

Utility shutdowns need coordinated notice and temporary measures where occupants are affected.

Why the Other Options Are Wrong

Option A: Turn off water without notice

Choice A (Turn off water without notice.) is rejected because the action skips the timing, documentation, or field-control step needed for Temporary water shutdown.

Option B: Record it only as a warranty item

In general project requirements, Record it only as a warranty item. is the wrong selection for Temporary water shutdown: it tries to bypass the Temporary water shutdown checkpoint.

Option C: Ask the supplier to approve the shutdown

The trap in C is Ask the supplier to approve the shutdown. That selection is wrong because it leaves out the controlling Temporary water shutdown result: Plan notice, duration, temporary service, approval, and restoration responsibilities.

Memory Technique

Pair temporary water shutdown with the real field trigger, then choose the response that produces Plan notice, duration, temporary service, approval, and restoration responsibilities.

Reference Hint

Open Construction Jobsite Management, 5th Ed. (2024); use by topic index - meetings / coordination / action items to confirm that Utility shutdowns need coordinated notice and temporary measures where occupants are affected.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.