A steel joist is set with less bearing than the erection plan requires. What is the proper response?
Correct Answer
A) Stop acceptance until bearing is corrected or engineered direction is obtained
Insufficient joist bearing is a structural installation issue and must be corrected or resolved by engineered direction before acceptance.
Why This Is the Correct Answer
Insufficient joist bearing is a structural installation issue and must be corrected or resolved by engineered direction before acceptance.
Why the Other Options Are Wrong
Option B: Base the steel joist bearing correction response on weld random scrap nearby
The trap in B is Weld random scrap nearby. That selection is wrong because the option does not produce the required Steel joist bearing correction outcome, Stop acceptance until bearing is corrected or engineered direction is obtained.
Option C: Select load the joist immediately for steel joist bearing correction
Choice C gives Load the joist immediately. Its specific error: it describes work from another assembly, while the Steel joist bearing correction item is asking for Stop acceptance until bearing is corrected or engineered direction is obtained.
Option D: The erection crew should hide the seat with ceiling work
Choice D (Hide the seat with ceiling work) is rejected because the action skips the timing, documentation, or field-control step needed for Steel joist bearing correction.
Memory Technique
Remember steel joist bearing correction by its jobsite consequence: the correct move points to Stop acceptance until bearing is corrected or engineered direction is obtained.
Reference Hint
Open Steel Construction Manual, 15th Ed.; Steel Deck Institute and Steel Joist Institute standard practice; use the index entry or section for "Joist bearing requirements" to confirm that Insufficient joist bearing is a structural installation issue and must be corrected or resolved by engineered direction before acceptance.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
Before the procurement meeting closes, who normally decides whether listed alternates are accepted when awarding the contract?
Next Question
The lead scheduler checks the procurement activity: wall cavities are ready for drywall before the required inspection occurs. What should the superintendent do?