The lead scheduler checks the procurement activity: wall cavities are ready for drywall before the required inspection occurs. What should the superintendent do?
Correct Answer
C) Hold cover work until the inspection is completed
Hold cover work until the inspection is completed is the contract-appropriate response: the distractors either bypass required review, conceal a defect, or create a payment or quality dispute in scenario item 243.
Why This Is the Correct Answer
Hold cover work until the inspection is completed is the contract-appropriate response
Why the Other Options Are Wrong
Option A: To cover and photograph while resolving inspection hold
In general project requirements, Cover and photograph is the wrong selection for Inspection hold: it points to Cover and photograph, but.
Option B: Ask for inspection signoff after the work has already been covered
The trap in B is Ask for signoff later. That selection is wrong because it answers the Inspection hold prompt with the wrong practical move.
Option D: Handle inspection hold by choosing to skip the inspection
Choice D (Skip the inspection) is rejected because it leaves the work at an informal or incomplete stage, while Inspection hold requires.
Memory Technique
Picture a pay line on the jobsite; inspection hold is solved by the action that leads to Hold cover work until the inspection is completed.
Reference Hint
Open Construction Jobsite Management, 5th Ed.; use the index entry or section for "Inspection hold points" to confirm that Hold cover work until the inspection is completed is the contract-appropriate response
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass