Why are steel deck side-lap attachments required?
Correct Answer
B) They connect adjacent deck sheets so the deck acts as detailed
Side-lap attachments connect adjacent sheets and support deck performance as detailed. They do not replace unrelated systems.
Why This Is the Correct Answer
Side-lap attachments connect adjacent sheets and support deck performance as detailed. They do not replace unrelated systems.
Why the Other Options Are Wrong
Option A: Accept the deck based on appearance and confirm side-lap attachment later
Choice A gives They replace concrete reinforcement. Its specific error: the option tries to substitute, waive, or delete the Steel deck sidelap purpose control; the item instead requires They connect adjacent deck sheets so the deck acts as detailed.
Option C: Treat side-lap attachment as a later repair item
In metals work, They waterproof the roof by themselves is the wrong selection for Steel deck sidelap purpose: it solves the wrong trade problem; the field result tied to Steel deck sidelap purpose is They connect adjacent deck sheets so the deck acts as detailed.
Option D: Accept visual appearance as the only field record for sidelap attachment
The trap in D is They set door-frame clearances. That selection is wrong because the option shifts to a different trade task; the tested Steel deck sidelap purpose function or field correction is They connect adjacent deck sheets so the deck acts as detailed; Steel deck s.
Memory Technique
Treat steel deck sidelap purpose like a labeled shelf; only the matching condition belongs with They connect adjacent deck sheets so the deck acts as detailed.
Reference Hint
Open Steel Construction Manual, 15th Ed.; Steel Deck Institute and Steel Joist Institute standard practice; use the index entry or section for "SDI side-lap attachment" to confirm that Side-lap attachments connect adjacent sheets and support deck performance as detailed.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass