A pay application shows $925,000 completed to date. Retainage is 5 percent and previous payments total $710,000. What current payment is due?
Correct Answer
A) $168,750
Net earned is $925,000 x 95% = $878,750. Current payment is $878,750 - $710,000 = $168,750. Other choices omit retainage, report gross earned less previous payments, or report net earned to date.
Why This Is the Correct Answer
Net earned is $925,000 x 95% = $878,750. Current payment is $878,750 - $710,000 = $168,750. Other choices omit retainage, report gross earned less previous payments, or report net earned to date.
Why the Other Options Are Wrong
Option B: $46,250
pay application current due, choice b: $46,250 is produced by $925,000 x 5 percent. The error is using that partial/alternate setup.
Option C: $215,000
pay application current due, choice c: $925,000 - $710,000 gives $215,000. That calculation subtracts those two listed numbers in that order.
Option D: $878,750
pay application current due, choice d: $878,750 is an intermediate from the steps (Net earned is 925000 x 95% = 878750.); the calculation continues to $168,750.
Memory Technique
Picture a dimension string labeled pay application current due: finish every operation before accepting $168,750.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Progress payment calculation" to confirm that Net earned is $925,000 x 95% = $878,750.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass