A proposed schedule of values puts 40 percent of the contract sum into mobilization, although the work value is much lower. What concern should the owner and architect review?
Correct Answer
D) The schedule may be front-loaded and should be revised to reflect reasonable work values
A schedule of values should reasonably allocate contract value to work items; excessive early values can front-load payments. Other choices make the SOV automatic, assign a false fixed percentage, or confuse it with scheduling.
Why This Is the Correct Answer
A schedule of values should reasonably allocate contract value to work items; excessive early values can front-load payments. Other choices make the SOV automatic, assign a false fixed percentage, or confuse it with scheduling.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
A rooftop unit schedule lists capacity in tons of cooling. In HVAC estimating, one ton of cooling equals what heat-transfer rate?
The bid form asks for a base bid and three alternates. How should the contractor submit alternate pricing?
A specification includes a $40,000 hardware allowance because final selections are pending. How is the allowance treated in the bid?
The earthwork section requires unit prices for unsuitable-soil removal. What is the contract-administration use of those unit prices?
Before the first progress payment, the owner requests a schedule of values. What is its main contract-payment function?
A signed change order is issued for added lobby millwork. Which contract effect should it state?
On the finish plan, locate room R358; then use the finish schedule. What remarks is listed?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A pay application shows $925,000 completed to date. Retainage is 5 percent and previous payments total $710,000. What current payment is due?
Next Question
A ceiling is being closed before the HVAC contractor has balanced branch airflows, and several balancing dampers will be inaccessible. What should be done?