A proposed schedule of values puts 40 percent of the contract sum into mobilization, although the work value is much lower. What concern should the owner and architect review?
Correct Answer
D) The schedule may be front-loaded and should be revised to reflect reasonable work values
A schedule of values should reasonably allocate contract value to work items; excessive early values can front-load payments. Other choices make the SOV automatic, assign a false fixed percentage, or confuse it with scheduling.
Why This Is the Correct Answer
A schedule of values should reasonably allocate contract value to work items; excessive early values can front-load payments. Other choices make the SOV automatic, assign a false fixed percentage, or confuse it with scheduling.
Why the Other Options Are Wrong
Option A: The schedule of values is automatically final once typed
The trap in A is The schedule of values is automatically final once typed. That selection is wrong because it points to The schedule of values is automatically final once typed, but.
Option B: Mobilization always equals 40 percent
Choice B gives Mobilization always equals 40 percent. Its specific error: Mobilization always equals 40 percent is a different published number than the cited Schedule of values review value; Schedule of values review and front loading supports The schedule may be front-loaded and should be revised to reflect reasonable work values.
Option C: The schedule of values replaces the construction schedule
Choice C (The schedule of values replaces the construction schedule) is rejected because it removes the controlling Schedule of values review requirement instead of meeting it.
Memory Technique
File schedule of values review under a flashing lip: condition first, number or duty second, answer The schedule may be front-loaded and should be revised to reflect reasonable work values.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Schedule of values review and front loading" to confirm that A schedule of values should reasonably allocate contract value to work items; excessive early values can front-load payments.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A pay application shows $925,000 completed to date. Retainage is 5 percent and previous payments total $710,000. What current payment is due?
Next Question
A ceiling is being closed before the HVAC contractor has balanced branch airflows, and several balancing dampers will be inaccessible. What should be done?