A proposed schedule of values puts 40 percent of the contract sum into mobilization, although the work value is much lower. What concern should the owner and architect review?

Correct Answer

D) The schedule may be front-loaded and should be revised to reflect reasonable work values

A schedule of values should reasonably allocate contract value to work items; excessive early values can front-load payments. Other choices make the SOV automatic, assign a false fixed percentage, or confuse it with scheduling.

Answer Options
A
The schedule of values is automatically final once typed
B
Mobilization always equals 40 percent
C
The schedule of values replaces the construction schedule
D
The schedule may be front-loaded and should be revised to reflect reasonable work values

Why This Is the Correct Answer

A schedule of values should reasonably allocate contract value to work items; excessive early values can front-load payments. Other choices make the SOV automatic, assign a false fixed percentage, or confuse it with scheduling.

Why the Other Options Are Wrong

Option A: The schedule of values is automatically final once typed

The trap in A is The schedule of values is automatically final once typed. That selection is wrong because it points to The schedule of values is automatically final once typed, but.

Option B: Mobilization always equals 40 percent

Choice B gives Mobilization always equals 40 percent. Its specific error: Mobilization always equals 40 percent is a different published number than the cited Schedule of values review value; Schedule of values review and front loading supports The schedule may be front-loaded and should be revised to reflect reasonable work values.

Option C: The schedule of values replaces the construction schedule

Choice C (The schedule of values replaces the construction schedule) is rejected because it removes the controlling Schedule of values review requirement instead of meeting it.

Memory Technique

File schedule of values review under a flashing lip: condition first, number or duty second, answer The schedule may be front-loaded and should be revised to reflect reasonable work values.

Reference Hint

Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Schedule of values review and front loading" to confirm that A schedule of values should reasonably allocate contract value to work items; excessive early values can front-load payments.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.