A single-ply roof crew finds damp cover board after an overnight storm, but the adhesive window is closing. What should the superintendent require?
Correct Answer
C) Wait until the substrate meets the manufacturer's dry and clean condition before adhering membrane
Membrane adhesion over damp substrate can trap moisture and compromise bond; the substrate should meet the manufacturer's dry, clean installation requirements. Other choices hide moisture or omit required attachment.
Why This Is the Correct Answer
Membrane adhesion over damp substrate can trap moisture and compromise bond; the substrate should meet the manufacturer's dry, clean installation requirements. Other choices hide moisture or omit required attachment.
Why the Other Options Are Wrong
Option A: The superintendent should install the membrane and rely on sun heat to dry trapped moisture
The trap in A is Install the membrane and rely on sun heat to dry trapped moisture. That selection is wrong because it points to Install the membrane and rely on sun heat to dry trapped moisture, but.
Option B: The superintendent should broadcast dry cement over the board and proceed
Choice B gives Broadcast dry cement over the board and proceed. Its specific error: it answers the Roof substrate moisture prompt with the wrong practical move.
Option D: Fasten only the seams and skip field adhesion
In thermal and moisture protection, Fasten only the seams and skip field adhesion is the wrong selection for Roof substrate moisture: the option delays or omits the controlling step.
Memory Technique
Tag the scene with roof substrate moisture: wrong actor or wrong timing means the fix is not Wait until the substrate meets the manufacturer's dry and clean condition before adhering membrane.
Reference Hint
Open Roofing Construction and Estimating, Atcheson, 1995/2022 reprint; use the index entry or section for "Roof membrane substrate condition before installation" to confirm that Membrane adhesion over damp substrate can trap moisture and compromise bond; the substrate should meet the manufacturer's dry, clean installation requirements.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass