NASCLAThermal/Moisturemedium4% of exam part

A single-ply roof crew finds damp cover board after an overnight storm, but the adhesive window is closing. What should the superintendent require?

Correct Answer

C) Wait until the substrate meets the manufacturer's dry and clean condition before adhering membrane

Membrane adhesion over damp substrate can trap moisture and compromise bond; the substrate should meet the manufacturer's dry, clean installation requirements. Other choices hide moisture or omit required attachment.

Answer Options
A
The superintendent should install the membrane and rely on sun heat to dry trapped moisture
B
The superintendent should broadcast dry cement over the board and proceed
C
Wait until the substrate meets the manufacturer's dry and clean condition before adhering membrane
D
Fasten only the seams and skip field adhesion

Why This Is the Correct Answer

Membrane adhesion over damp substrate can trap moisture and compromise bond; the substrate should meet the manufacturer's dry, clean installation requirements. Other choices hide moisture or omit required attachment.

Why the Other Options Are Wrong

Option A: The superintendent should install the membrane and rely on sun heat to dry trapped moisture

The trap in A is Install the membrane and rely on sun heat to dry trapped moisture. That selection is wrong because it points to Install the membrane and rely on sun heat to dry trapped moisture, but.

Option B: The superintendent should broadcast dry cement over the board and proceed

Choice B gives Broadcast dry cement over the board and proceed. Its specific error: it answers the Roof substrate moisture prompt with the wrong practical move.

Option D: Fasten only the seams and skip field adhesion

In thermal and moisture protection, Fasten only the seams and skip field adhesion is the wrong selection for Roof substrate moisture: the option delays or omits the controlling step.

Memory Technique

Tag the scene with roof substrate moisture: wrong actor or wrong timing means the fix is not Wait until the substrate meets the manufacturer's dry and clean condition before adhering membrane.

Reference Hint

Open Roofing Construction and Estimating, Atcheson, 1995/2022 reprint; use the index entry or section for "Roof membrane substrate condition before installation" to confirm that Membrane adhesion over damp substrate can trap moisture and compromise bond; the substrate should meet the manufacturer's dry, clean installation requirements.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.