During turnover document review, what does bid responsiveness primarily measure?
Correct Answer
D) Conformance with material bidding requirements
Conformance with material bidding requirements is the correct meaning of responsiveness in this construction context for concept item 422. Other choices: the distractors describe unrelated administration, payment, or closeout ideas.
Why This Is the Correct Answer
Conformance with material bidding requirements is the correct meaning of responsiveness in this construction context for concept item 422.
Why the Other Options Are Wrong
Option A: Select ability to perform for responsiveness
In procurement and contracting, Ability to perform is the wrong selection for Responsiveness: it answers the Responsiveness prompt with the wrong practical move.
Option B: Select final completion for responsiveness
The trap in B is Final completion. That selection is wrong because it leaves out the controlling Responsiveness result.
Option C: Apply weather delay to the responsiveness condition
Choice C gives Weather delay. Its specific error: the choice would not get the project.
Memory Technique
Attach responsiveness to a pay line: remember the function, then the wording Conformance with material bidding requirements.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Bid responsiveness" to confirm that Conformance with material bidding requirements is the correct meaning of responsiveness in this construction context for concept item 422.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
When the reviewer opens the backup package, a schedule update shows one late activity has float and another delays completion. Where is recovery focused first?
Next Question
A single-ply roof crew finds damp cover board after an overnight storm, but the adhesive window is closing. What should the superintendent require?
