When the reviewer opens the backup package, a schedule update shows one late activity has float and another delays completion. Where is recovery focused first?
Correct Answer
C) On the critical-path delay
On the critical-path delay is the contract-appropriate response: the distractors either bypass required review, conceal a defect, or create a payment or quality dispute in scenario item 298.
Why This Is the Correct Answer
On the critical-path delay is the contract-appropriate response
Why the Other Options Are Wrong
Option A: Limit critical path to on the float activity
The trap in A is On the float activity. That selection is wrong because it points to On the float activity, but.
Option B: Base the critical path response on on completed work
Choice B gives On completed work. Its specific error: it answers the Critical path prompt with the wrong practical move.
Option D: Make on easiest paperwork the answer for critical path
In general project requirements, On easiest paperwork is the wrong selection for Critical path: the choice would not get the project to On the critical-path delay, which is the Critical path result verified by the source.
Memory Technique
Picture a closeout folder on the jobsite; critical path is solved by the action that leads to On the critical-path delay.
Reference Hint
Open Construction Jobsite Management, 5th Ed.; use the index entry or section for "Critical path recovery" to confirm that On the critical-path delay is the contract-appropriate response
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass