A 6-ft trench is not entirely in stable rock. Which protective-system rule controls?
Correct Answer
B) 5 ft or deeper unless an exception applies
Because the trench is deeper than 5 ft and not entirely in stable rock, cave-in protection is generally required.
Why This Is the Correct Answer
Because the trench is deeper than 5 ft and not entirely in stable rock, cave-in protection is generally required.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
A rooftop unit schedule lists capacity in tons of cooling. In HVAC estimating, one ton of cooling equals what heat-transfer rate?
The bid form asks for a base bid and three alternates. How should the contractor submit alternate pricing?
A specification includes a $40,000 hardware allowance because final selections are pending. How is the allowance treated in the bid?
The earthwork section requires unit prices for unsuitable-soil removal. What is the contract-administration use of those unit prices?
Before the first progress payment, the owner requests a schedule of values. What is its main contract-payment function?
A signed change order is issued for added lobby millwork. Which contract effect should it state?
On the finish plan, locate room R358; then use the finish schedule. What remarks is listed?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A single-ply roof crew finds damp cover board after an overnight storm, but the adhesive window is closing. What should the superintendent require?
Next Question
The contract carried 900 cy of undercut at $42/cy. Final measured quantity is 760 cy. What deductive adjustment is due for the underrun?