Pipe bedding stockpile is mixed with large debris. What should the inspector require?

Correct Answer

D) Reject or screen/replace bedding material so it meets specified gradation and cleanliness.

Bedding must meet specified material requirements to support and protect pipe.

Answer Options
A
The site crew should use debris as extra support
B
Handle bedding contaminated by choosing to place it only under joints
C
Limit bedding contaminated to record it at warranty only
D
Reject or screen/replace bedding material so it meets specified gradation and cleanliness.

Why This Is the Correct Answer

Bedding must meet specified material requirements to support and protect pipe.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.