What is the purpose of proofrolling a prepared subgrade?

Correct Answer

C) Identify soft, pumping, or unstable areas before placing the next layer.

Proofrolling exposes weak subgrade areas before they are covered.

Answer Options
A
Measure bid security
B
The site crew should approve final warranties
C
Identify soft, pumping, or unstable areas before placing the next layer.
D
The site crew should replace compaction testing

Why This Is the Correct Answer

Proofrolling exposes weak subgrade areas before they are covered.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.