Proofrolling reveals pumping soil under a planned pavement area. What should the site contractor do?

Correct Answer

A) Notify the responsible party and correct or stabilize the unsuitable area before base placement.

Pumping subgrade indicates instability that must be addressed before cover.

Answer Options
A
Notify the responsible party and correct or stabilize the unsuitable area before base placement.
B
Place base immediately to bridge it
C
The contractor should ignore if the surface dries by afternoon
D
The contractor should use the area for concrete washout, leaving soft subgrade proofroll unverified

Why This Is the Correct Answer

Pumping subgrade indicates instability that must be addressed before cover.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.