Mud is being tracked from the project entrance onto a public street. What should the superintendent do?

Correct Answer

D) Clean the street and improve the stabilized entrance or wheel-cleaning controls.

Trackout must be cleaned and controls adjusted so sediment is not discharged off site.

Answer Options
A
Wash mud into the storm inlet, leaving sediment trackout response unverified
B
The superintendent should wait until final paving
C
Resolve sediment trackout response after choosing to move the silt fence uphill
D
Clean the street and improve the stabilized entrance or wheel-cleaning controls.

Why This Is the Correct Answer

Trackout must be cleaned and controls adjusted so sediment is not discharged off site.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.