Where should concrete truck washout occur on a stormwater-controlled site?

Correct Answer

D) In a designated contained washout area away from storm drains and waters

Concrete washout is contained in a designated area so high-pH slurry does not reach storm drains or waters.

Answer Options
A
Apply at the nearest catch basin to the concrete washout containment condition
B
Make on finished pavement without containment the answer for concrete washout containment
C
Make in the pipe bedding trench the answer for concrete washout containment
D
In a designated contained washout area away from storm drains and waters

Why This Is the Correct Answer

Concrete washout is contained in a designated area so high-pH slurry does not reach storm drains or waters.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.