What is the purpose of storm-drain inlet protection during construction?

Correct Answer

D) Keep sediment from entering the storm sewer during construction

Storm-drain inlet protection traps or filters sediment before runoff enters the storm sewer.

Answer Options
A
The site crew should increase potable pressure
B
The site crew should replace excavation shoring
C
Base the storm drain inlet sediment control response on measure concrete slump
D
Keep sediment from entering the storm sewer during construction

Why This Is the Correct Answer

Storm-drain inlet protection traps or filters sediment before runoff enters the storm sewer.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.