Mud is being tracked from the stabilized construction entrance onto a public street. What is the correction?

Correct Answer

D) Clean the street and improve entrance or wheel-cleaning controls

Trackout should be cleaned promptly and entrance controls improved so sediment is not carried off site.

Answer Options
A
Wash the mud into a storm drain
B
The site crew should wait until final paving
C
The site crew should remove all inlet protection
D
Clean the street and improve entrance or wheel-cleaning controls

Why This Is the Correct Answer

Trackout should be cleaned promptly and entrance controls improved so sediment is not carried off site.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.