A pipe run shows voids under the haunches before backfill. What should happen?

Correct Answer

D) Correct bedding support before the pipe is covered

Voids under pipe haunches can allow settlement and grade problems; bedding support should be corrected before cover.

Answer Options
A
Accept because water may pass
B
Select flush after occupancy for pipe bedding void
C
Make place slab first the answer for pipe bedding void
D
Correct bedding support before the pipe is covered

Why This Is the Correct Answer

Voids under pipe haunches can allow settlement and grade problems; bedding support should be corrected before cover.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.