A perimeter sediment control has a gap where runoff leaves the disturbed area. What should be done?

Correct Answer

C) Close or protect the gap before runoff carries sediment off site

Perimeter controls must be continuous or otherwise protected where runoff leaves disturbed soil.

Answer Options
A
The site crew should wait for paving
B
Select pump sediment downstream for perimeter sediment gap
C
Close or protect the gap before runoff carries sediment off site
D
The site crew should remove all perimeter controls

Why This Is the Correct Answer

Perimeter controls must be continuous or otherwise protected where runoff leaves disturbed soil.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.