A newly installed gravity sewer has a low spot that holds water during testing. What should be corrected?

Correct Answer

C) Regrade or relay the pipe so it maintains required slope

Gravity sewer low spots hold water and indicate grade/bedding problems that should be corrected before cover.

Answer Options
A
Accept it because some water passes
B
The site crew should hide the low spot with bedding
C
Regrade or relay the pipe so it maintains required slope
D
The site crew should wait until after slab placement

Why This Is the Correct Answer

Gravity sewer low spots hold water and indicate grade/bedding problems that should be corrected before cover.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.