Before excavation begins, what must be done for known underground installations?

Correct Answer

A) Determine estimated utility locations and protect or support them as needed

Underground installations must be located or estimated before excavation and then protected, supported, or removed as needed.

Answer Options
A
Determine estimated utility locations and protect or support them as needed
B
Apply assume drawings are exact to the underground utility locate condition
C
The site crew should cut all lines to confirm depth
D
The site crew should wait until backfill to notify utilities

Why This Is the Correct Answer

Underground installations must be located or estimated before excavation and then protected, supported, or removed as needed.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.