Backhoe spoil is accumulating directly beside the trench because the haul route is muddy. Workers are placing pipe in the bottom of the cut. What correction should be made?
Correct Answer
A) Move the spoil at least 2 ft from the edge or restrain it so it cannot roll or fall into the trench
Spoil near an excavation edge creates falling-material and surcharge hazards; OSHA requires keeping it at least 2 ft back or retaining it. Other choices do not remove the surcharge or protect employees in the trench.
Why This Is the Correct Answer
Spoil near an excavation edge creates falling-material and surcharge hazards; OSHA requires keeping it at least 2 ft back or retaining it. Other choices do not remove the surcharge or protect employees in the trench.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
A rooftop unit schedule lists capacity in tons of cooling. In HVAC estimating, one ton of cooling equals what heat-transfer rate?
The bid form asks for a base bid and three alternates. How should the contractor submit alternate pricing?
A specification includes a $40,000 hardware allowance because final selections are pending. How is the allowance treated in the bid?
The earthwork section requires unit prices for unsuitable-soil removal. What is the contract-administration use of those unit prices?
Before the first progress payment, the owner requests a schedule of values. What is its main contract-payment function?
A signed change order is issued for added lobby millwork. Which contract effect should it state?
On the finish plan, locate room R358; then use the finish schedule. What remarks is listed?