An excavator uncovers an unmarked duct bank where the drawings show only abandoned telephone service. What should the site superintendent require before digging continues?
Correct Answer
C) Stop work in the conflict area, protect the exposure, and verify the utility status and relocation method
Unknown utilities should be treated as active until verified; work should stop in the conflict area while the utility is protected and the owner or locator confirms the correct action. Other choices risk utility damage, injury, or concealed changed conditions.
Why This Is the Correct Answer
Unknown utilities should be treated as active until verified; work should stop in the conflict area while the utility is protected and the owner or locator confirms the correct action. Other choices risk utility damage, injury, or concealed changed conditions.
Why the Other Options Are Wrong
Option A: Pull the duct bank aside with the bucket
Choice A gives Pull the duct bank aside with the bucket. Its specific error: the option does not produce the required Utility conflict outcome, Stop work in the conflict area, protect the exposure, and verify the utility status and relocation method.
Option B: Assume it is abandoned because the plan note says so
Choice B (Assume it is abandoned because the plan note says so) is rejected because it points to Assume it is abandoned because the plan note says so, but.
Option D: Backfill immediately and omit the conflict from the daily report
The trap in D is Backfill immediately and omit the conflict from the daily report. That selection is wrong because it leaves out the controlling Utility conflict result: Stop work in the conflict area, protect the exposure, and verify the utility status and relocation method.
Memory Technique
Use the phrase "problem, control, result" for utility conflict; the result side is Stop work in the conflict area, protect the exposure, and verify the utility status and relocation method.
Reference Hint
Open Pipe and Excavation Contracting, 2011; use the index entry or section for "Existing utility protection during excavation" to confirm that Unknown utilities should be treated as active until verified; work should stop in the conflict area while the utility is protected and the owner or locator confirms the correct action.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
