A trench pump is discharging cloudy water toward a storm drain. What should be done?
Correct Answer
B) Route discharge through approved sediment controls or a settling/filtering method.
Turbid dewatering discharge must be treated or routed through approved controls.
Why This Is the Correct Answer
Turbid dewatering discharge must be treated or routed through approved controls.
Why the Other Options Are Wrong
Option A: Discharge faster before inspection
Choice A gives Discharge faster before inspection. Its specific error: it leaves out the controlling Dewatering turbid water result: Route discharge through approved sediment controls or a settling/filtering method.
Option C: Pump into the sanitary sewer without approval
In site construction, Pump into the sanitary sewer without approval. is the wrong selection for Dewatering turbid water: it leaves the work at an informal or incomplete stage, while Dewatering turbid water requires Route discharge through approved sediment controls or a settling/filtering method.
Option D: Ignore because water is from rain
The trap in D is Ignore because water is from rain. That selection is wrong because the option delays or omits the controlling step.
Memory Technique
Picture a switch on the jobsite; dewatering turbid water is solved by the action that leads to Route discharge through approved sediment controls or a settling/filtering method.
Reference Hint
Open Developing Your Stormwater Pollution Prevention Plan, EPA 833-R-06-004, 2007; use the index entry or section for "EPA 833-R-06-004 - erosion and sediment controls" to confirm that Turbid dewatering discharge must be treated or routed through approved controls.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
The estimate carried $485,000 for roofing. The subcontract is bought for $462,500 with aligned scope. What buyout savings are shown?
Next Question
An excavator uncovers an unmarked duct bank where the drawings show only abandoned telephone service. What should the site superintendent require before digging continues?