A storm cuts rills down a newly graded slope. What is the appropriate response?

Correct Answer

D) Repair erosion, stabilize the slope, and improve runoff controls.

Erosion damage indicates stabilization and runoff controls are inadequate.

Answer Options
A
The site crew should wait until final acceptance
B
Base the erosion after storm response on blade sediment into the creek
C
The site crew should remove all slope drains
D
Repair erosion, stabilize the slope, and improve runoff controls.

Why This Is the Correct Answer

Erosion damage indicates stabilization and runoff controls are inadequate.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.