The drywall lead verifies a control-joint layout: a cheaper product differs from the specified basis and has not been approved. What should happen before purchase?

Correct Answer

C) Submit it through the substitution procedure and wait for approval

Submit it through the substitution procedure and wait for approval is the contract-appropriate response: the distractors either bypass required review, conceal a defect, or create a payment or quality dispute in scenario item 396.

Answer Options
A
The contractor should install first; without required owner or contract approval
B
Base the substitution response on mark it as an RFI only
C
Submit it through the substitution procedure and wait for approval
D
Close contract execution first and resolve the substitution record later

Why This Is the Correct Answer

Submit it through the substitution procedure and wait for approval is the contract-appropriate response

Why the Other Options Are Wrong

Option A: The contractor should install first; without required owner or contract approval

The trap in A is Install first; without required owner or contract approval. That selection is wrong because it leaves the work at an informal or incomplete stage, while Substitution requires.

Option B: Base the substitution response on mark it as an RFI only

Choice B gives Mark it as an RFI only. Its specific error: the option delays or omits the controlling step.

Option D: Close contract execution first and resolve the substitution record later

In procurement and contracting, Delete the product is the wrong selection for Substitution: it removes the controlling Substitution requirement instead of meeting it.

Memory Technique

Remember substitution by its jobsite consequence: the correct move points to Submit it through the substitution procedure and wait for approval.

Reference Hint

Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Substitution procedure" to confirm that Submit it through the substitution procedure and wait for approval is the contract-appropriate response

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.