What risk does a bid bond primarily protect the owner against?
Correct Answer
A) The successful bidder refusing to enter the contract or furnish required bonds.
Bid security protects the owner if the successful bidder does not honor the bid or provide required bonds.
Why This Is the Correct Answer
Bid security protects the owner if the successful bidder does not honor the bid or provide required bonds.
Why the Other Options Are Wrong
Option B: Treat an architect's missing detail as the risk covered by the bid bond
Choice B (The architect missing a detail.) is rejected because it points to The architect missing a detail. but.
Option C: Treat the owner's occupancy change as the risk covered by the bid bond
In procurement and contracting, The owner changing occupancy plans. is the wrong selection for Bid bond purpose: it answers the Bid bond purpose prompt with the wrong practical move.
Option D: Treat early supplier shipment as the risk covered by the bid bond
The trap in D is The supplier shipping early. That selection is wrong because it leaves out the controlling Bid bond purpose result: The successful bidder refusing to enter the contract or furnish required bonds.
Memory Technique
File bid bond purpose under a panel space: condition first, number or duty second, answer The successful bidder refusing to enter the contract or furnish required bonds.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Bid security" to confirm that Bid security protects the owner if the successful bidder does not honor the bid or provide required bonds.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
